Future Controls was recently involved in Testing and Balancing a newly constructed twenty-two story hotel that was built on top of an existing five story structure in downtown Charlotte, North Carolina.  As part of the Test and Balance of the facility the elevator shafts and the stairwells were required to meet the county code pressure requirements during a fire alarm.

The stairwells and ...